11 5 Year Capital Programme 2026/27 to 2030/31
PDF 141 KB
To consider the report of the Accountancy Services Manager (enclosed).
Additional documents:
Decision:
RECOMMENDATIONS TO COUNCIL
1. That the 5 Year Capital Programme for 2026/27 to 2030/31, be approved.
2. That the application of capital resources of £5,066,884 for 2026/27, including a borrowing requirement of £2,627,099 be approved.
3. That the Capital Strategy 2026/27 to 2030/31 be approved.
Reasons:
1. To obtain approval for the proposed level of capital expenditure in 2026/27 and the suggested method of financing that expenditure.
2. To provide a longer-term forecast of capital expend
3. To ensure compliance with the Prudential Code
Minutes:
Considered – Report of the Finance Group Manager.
Other Options Considered:
None. It is important to produce a 5-year Capital Programme as a minimum requirement of the Capital Strategy, and that the programme aligns with the Council’s Medium Term Financial Strategy.