Issue - decisions

Quarter 1 Capital Programme Review 2024/25

16/09/2024 - Quarter 1 Capital Programme Review 2024/25

RECOMMENDATIONS TO COUNCIL

 

1.    That the report be accepted.

 

2.    That the latest Capital Programme for 2024/25, totalling £8,362,558, be accepted.

 

Reasons:

 

1.    To ensure that the Council has adequate resources in place to meet its capital expenditure commitments.

 

2.    To reflect additions or other changes to the Capital Programme since it was approved by Council on 27th February 2024, including the carry forward of unspent budget from 2023/24.